Supercharger - Szczecin, Poland

C: Poland
City: Szczecin
Street: Andrzeja Struga 42
Construction date: started 03.2024


5 Likes

thanks @daginski added now

2 Likes

How we know it will be 8? We have information about 12.

I didn’t know. We have to enter a number in the system and used 8 as a placeholder as it is a common minimum install size. As you think it is 12 I have changed it to that.

Do you know what is an avarage time from start to open charging station?

Update

2 Likes

Last year it was about 3-4 months after they started construction. Supercharger Warsaw

More due to bureaucracy, the station was ready earlier, if this moment is accelerated, then I think 1-2 months.

One thing I have confirmed after looking at superchargers around the world is that bureaucracy exists everywhere.
It could be worse though Portugal is the world capital of bureaucracy for supercharger installs.

1 Like

Your foto again:)

1 Like

It will be Poland first V4 charger

2 Likes

3 Likes

any news?

1 Like
1 Like

Any updates on this? :sweat_smile:

1 Like

Yesterday they did open in Billund (DK), it took around 25 days from the day they were ready to offical opening.

8 Likes

Dzieje sie

I’m curious about the opening date of these superchargers… hopefully in May.

It’s unlikely, UDT has 30 days to review the documents after the station is ready for operation, and in the photo above there is still work going on there, my bet is June. May will be a huge luck.

1 Like

Even July :P, in Denmark it took 25 days and we know how it works in Poland.

1 Like