It is ready now. I don’t know what’s in the way to let it fly. The entry to parking lot is still blocked by tapes and so is the SC. You can see, that even the transformator station is finished which wasn’t the case last week.
Thx alot for the update
So let‘s wait & see…
The delay is occurring because the grid operator currently cannot coordinate timely commissioning dates due to a lack of personnel.
1 Like