Construction of a supercharger in Hradec Králová near the Albert shopping center is already underway.
Thank you for the photos. I hope it will be in service soon ![]()
After one month - nothing. I guess this is the way how to be the leader in laziness. Big shame to the representatives of the state. Czech government - what a waste of money and absence of goal.
There is a planned power outage in the area around the SCH substation on Thursday. I don’t know if it’s related to the substation’s connection to the HV, but I hope so.
so far nothing, cz = country of future ![]()
On August 21st, the transformer station was connected to high voltage. Now the traffic signs have been added. Everything looks like it’s done, but they still haven’t been turned on.
An excerpt from a local newspaper article:
“A total of 24 charging stations are planned to be built in two construction phases. The finishing phase of the first stage is currently underway, during which twelve charging stations and a transformer station are being built. We expect the launch of Stage 1 to take place in the last quarter of this year.”
Source: V hradeckých Kuklenách vzniká velká nabíjecí stanice Tesly - Hradecký deník