Finally, there is a lot of activity on the building site at Ottergemsesteenweg-zuid 702, Gent. Even though the permit for the construction of 24 V4
Superchargers was final at the end of August 2024, the installation apparently had to await the groundwork for a brand new gas station planned at the same address that will share its driveway with the Tesla superchargers. The dewatering permit for these ground works was only granted at the end of June 2025.