Supercharger - Gent, Belgium

Tesla launched a permit request for a SuC at Van der Valk hotel in Gent, Belgium. 24 stalls (V4). Location: 51.0181, 3.7367
Permit link: https://omgevingsloketinzage.omgeving.vlaanderen.be/2024062230

1 Like


Tesla Ghent Belgium at Van Der Valk hotel Ghent has asked for a permit

Address Ottergemsesteenweg-Zuid 702, 9000 Ghent , Belgium

https://omgevingsloketinzage.omgeving.vlaanderen.be/2024062230/inhoud-aanvraag

2 Likes

Finally, there is a lot of activity on the building site at Ottergemsesteenweg-zuid 702, Gent. Even though the permit for the construction of 24 V4
Superchargers was final at the end of August 2024, the installation apparently had to await the groundwork for a brand new gas station planned at the same address that will share its driveway with the Tesla superchargers. The dewatering permit for these ground works was only granted at the end of June 2025.


3 Likes

Last week I was passing by after work and they were doing the groundwork for the gas station.

Glad to see they have started with the superchargers :+1:t2:

Supercharger Gent

Net nog eens gepasseerd in Gent.
Foto’s uploaden duurt hier een eeuwigheid blijkbaar…

Almost done

1 Like

18 days later… still the same… odd

Oil beats electricity:

Tinq unmanned gas station ready to open but awaiting completion of Tesla Supercharger Gent

2 Likes

1 Like

Tinq apparently couldn’t wait to open, as the first gasoline was already flowing from the pump on Thursday.

A new exit has been built, leading to the last section of the one-way road Akkerhage

Movable LED panel in front of the unfinished entryway to the Tesla Superchargers

=> Let’s hope that during Tinq’s opening celebration week (December 8-14), the Supercharger Gent will also be able to open?

Status Quo for the last 4 weeks now, the last mile is apparently the hardest…

1 Like

Can’t wait!

Thursday they were working on the superchargers but no idea what exactly they were doing.

At that time, the gas station was still closed.

Van Der Valk has said that the intention is that everything would be finished by mid-December…

1 Like


Closing the gap…


Construction closure to Hendriks Gent


Bring on those two trees !

4 Likes

4 Likes


Curious to see how this drainage will be integrated (bis) ?


This is how the drainage will be incorporated (side of Van der Valk external parking lot)


Is all that’s missing here a layer of asphalt => Yes that’s right :wink:


New asphalt for Van der Valk external parking lot


Almost done, including the 6 stalls at the back :wink:

3 Likes

En de chargers nog aansluiten zeker? Maandag was dat nog niet…

Just missing some asphalt and white paint for the lines :wink:

I went looking today and two trucks were busy laying asphalt.

1 Like

Asphalt is ready :blush:

Other roadworks are ready; the last excavator left the moment I arrived. They’re currently commissioning the chargers (should be done today).

Next steps (according to the person who was commissioning):

  • Installing and testing internet connectivity to the chargers (done by a Tesla employee).
  • Chargers should open very soon (probably this or next week) :tada:

The person on site was also very happy with the new chargers—he said he’ll charge a lot at the new location with his Tesla :sweat_smile: